Sheffield Resources unveils Thunderbird Mineral Sands project progress

19 Sept 20237:06

Sheffield Resources unveils Thunderbird Mineral Sands project progress

General information only. ausbiz videos are general information only, produced by Ausbiz TV Pty Ltd, a media business that doesn’t give financial advice. They don’t take into account your objectives, financial situation or needs. Consider whether it’s right for you and read the PDS and TMD before acting on anything you watch.

About this video

Bruce Griffin of Sheffield Resources sheds light on the financial intricacies of the Thunderbird Mineral Sands project. Despite escalation in costs since 2019, Bruce explains how careful project scaling down and adept engineering have resulted in sticking to initial capital cost predictions. The project plans to mine zircon, sold as a concentrate, and a high-quality magnetic concentrate containing Ilmenite as its secondary output, with both ready for further processing. Zircon finds its applications mainly in the ceramics industry, delivering optical properties to glossy sanitary products and thermal industries.

Bruce also speaks on Sheffield's equal partnership with Yan Steel, a Chinese Steel firm. This partnership facilitates Yan's usage of magnetic concentrates for titanium dioxide pigment production, while the latter aids with most equity during the construction phase. Beyond the Thunderbird Mineral Sands project, Bruce imparts knowledge about Sheffield's involvement in the South Atlantic project in Brazil, intending to maximize the value and gain approval on the first option, with a target towards complete project acquisition.

Progress-wise, Bruce affirms that the Thunderbird project is progressing as expected, anticipating a shift from construction to operations by the year's final quarter, with the first shipment scheduled for the first quarter of 2024.

Find the full unedited transcript of this interview below:

Well, let's get stock specific again now. Sheffield Resources has announced that the construction of 50% owned Thunderbird Mineral Sands project in Northern WA is rapidly approaching 90% completion and on track to commence commissioning during the second half of this year. Let's get to the specifics with Executive Chairman, Bruce Gryphon. Bruce, welcome to Aspis. Thanks very much for joining us. Talk us then a little more in terms of on you obviously on track there. You're pleased with the progress you got there.

0:32

Yeah very, very pleased. I think quite unusual for someone to actually complete a project on time and on budget and and WA. So we're very pleased with where we are and and very happy to be in the commissioning phase now. Yeah, you talk about coming in on budget then I mean how difficult it has that been given those cost pressures you know in particular labour. We know that you've had significant shortages don't certainly there in in WA but moreover I guess coming out of COVID just how difficult that's been.

1:04

Yeah, I mean I think there's a couple of things there. One is we we did see some cost pressure in in our original capital cost estimate but one thing we did was descope the project. So we we took a few elements out of the project which reduced the capital costs. So we had seen cost inflation from 2019 through 2022 when we made the final investment decision. But what we've been able to do is then execute the project you know on

1:34

against the budget at at the time we made the investment. So you know combination of a very mature engineering on the project meant that the fixed price estimate from from GR engineering they were able to execute against that which was very pleasing and we self executed a bunch of the of the minor infrastructure works which seemed to help us manage the costs as well.

1:59

Bruce Willis, a little more than about the project there, Thunderbird Mineral Sands, what you're actually and reminding there,

2:08

yeah, so it's a it's a mineral sands mine. Our our primary product by value is, is Zircon. We'll be selling the Zircon in a concentrate and then we have a second main product which we call magnetic concentrate contains a high quality Illuminati. So we're basically only producing concentrates. It means our process is relatively simple. So you know we're we're we're we're basically mining and doing you know concentration to extract the heavy mineral sands and then splitting those into into a couple of streams and and shipping them for others to do further processing. OK. So, So what are they the likes of zircon, what's that checker used for?

2:51

So zircon main applications for zircon is in ceramics. So about half of zircon roughly is used in ceramics and and it's used, it's used as a pacifier and it's also part of what, you know, it's what you think of shiny white things in a bathroom. Zircon is, is, is an important part of what gives them that that those optical qualities and then there's a number of sort of

3:19

sort of thermal related application. So effectively it can be used as a refractory and it's used for casting type applications. So it can be used for hot metal casting. And then there's a couple of chemical applications as well. So it's a sort of mixture of industrial and consumer related applications. So you do do have that 5050 joint venture there with Yan Steel. What was that amount to

3:49

so the the idea behind the Yang still joint venture. Yang still is a Chinese steel company that that building a a titanium dioxide pigment business and they were looking for feedstocks. So they are gonna take our magnetic concentrate and and process that in their facilities to to to make titanium dioxide. The basis of the joint venture was off take. So they are taking the, the magnetic concentrate as I said and then they provided the majority of the equity for the construction phase and in exchange for that they've ended up as the 50% owner of the of the project. Alright. So that's there in WRC. You've also got interest in a project in Brazil, the South Atlantic project. Tell us more about that

4:37

yeah I'm the the the South Atlantic project is something that we we've effectively entered into an option agreement on earlier this year. It's a project I know very well and the idea was that we're we're we're basically spending a bit of money alongside the current owners about two and a half million US in our case to to really prove up the value proposition there. A lot of works being done on that project, again a mineral sands project, but it's been done on a private company. So it wasn't suitable for police to things like the ASX. So we're doing a big drilling programme later this year which should see us convert the expiration target which is somewhere between 500 and 700 million tonnes of ore into a resource and sort of confirm the value with a feasibility study. And then in parallel there are some important approvals that are due to be granted during the initial option.

5:36

Which runs until August next year. And and at that stage, if we like the value proposition and the risk profile, then we have an option to acquire an initial 20% by paying another 12 and a half million US And then we actually have a framework agreement that allows us to go to 80% through development and ultimately to acquire 100% of that project, OK. So in the meantime, of course your focus is on Thunderbird mineral sands project, You're saying you're on budget, you're also on time. What is the timing there in terms of production,

6:11

Yes, a key sort of key milestones coming up now. You know said we are commissioning now which is really the getting the process plant up and ready for ore where they are Dry mining unit was delivered to site earlier this month. That'll be installed over the next month or so and then basically getting ready so that we can put or in the plant in the fourth quarter of this year. That's really what we consider the transition from construction to to to to operations. We should be making concentrates and putting them in the stockpiles during quarter four of this year and then targeting an initial shipment to customers early in the new year or or or effectively in Q1 of 2024. So we're sort of you know a a matter of less than six months away from cash flow and sort of less than three months away from first production.