Sign inJoin free

Watch / CEOs & MDs

Adriatic Metals nears project completion

25 July 20235:35

Adriatic Metals nears project completion

General information only. ausbiz videos are general information only, produced by Ausbiz TV Pty Ltd, a media business that doesn’t give financial advice. They don’t take into account your objectives, financial situation or needs. Consider whether it’s right for you and read the PDS and TMD before acting on anything you watch.

About this video

Adriatic Metals' (ADT) Paul Cronin dicsusses the company's progress at it's Vares Silver Project in Bosnia & Herzegovina, as well as updates for the June 2023 quarter.

Paul says construction at the project reached 84% completion, with the first ore mined at Rupice and stockpiled on July 15. However, he says lower decline development stood at 695m and upper decline at 601m as of July 20, indicating potential delays. The first ore drive was achieved by the end of Q2.

Paul says the company faced staffing challenges, with a staff headcount increase to 267, and 398 contractors at the end of Q2.

Regarding exploration, drilling in the Rupice Northwest area revealed a 'Lower Zone' with copper gold-rich minerals and other valuable elements. However, Paul says challenges were seen in the gap between Rupice and RNW deposits.

Financially, Adriatic Metals estimates the final project cost at $182m, with the final Orion debt drawdown of $30m expected in Q3. The company's cash balance was $85.6m as of June 30, with further capex and exploration outflows expected pre-production.

Paul is optimistic about the progress made, including first ore mining and accelerating the development plan.

More like this

We value your privacy

We use essential cookies to make the site work. Non-essential cookies help us improve the experience. You can accept or reject non-essential cookies. Privacy policy